Morley provided concrete subcontractor services and reinforcing steel for a new hospital bed tower adjacent to an existing operational hospital, including scope for the elevator core.
Construction included more than 11,000 cubic yards of concrete for pile caps and footings, concrete fill over metal deck, slab on grade, cooling tower yard, site walls, and footings around the building footprint. The building consists of a structural steel frame with seven levels of metal decking.
Project Details:
- 296,000 gsf
- 11,000 cy of concrete
Owner:
HCA Management L.P.
Architect:
Perkins + Will